news from Mainz
  • Amazing developments, progress, constructions...
  • MESA commissioning possibly delayed by a few months (cryo valves delivery)
  • target cell in planning phase
IRFU questions to Mainz
  • target support : sketch of planned approach can be shared. Does this also accomodate the target mask? (-> Boris)
  • availability of neutron (TID, RadFET) diagnostics? Beam current for Rahima's QDC tests in A1? Possible to find back the dose accumulated during the beamtime in June 2023? (-> Rahima, Jurgen)
  • MESA beam tube and flange dimensions? (-> Kurt, ...?)
  • picture of shielding rails in scattering chamber (-> Boris)
  • beam polarity pattern and signals?
  • Availability of clean GND (EARTH) in the P2 experimental hall
Mainz questions to IRFU
  • How expell the Isobutane? exhaust setup : ~20m high, 40 or 80 mm diameter. IRFU : Clarify ATLAS, Clas12 setups; transmit to P2
  • short-term storage (~100 Tb) : decide within 6 months. Long-term : decide by 2026. Clarify commissioning strategy in this respect.