Amazing developments, progress, constructions...
 - 
MESA commissioning possibly delayed by a few months (cryo valves delivery)
 - 
target cell in planning phase
 
IRFU questions to Mainz
- 
target support : sketch of planned approach can be shared. Does this also accomodate the target mask? (-> Boris)
 - 
availability of neutron (TID, RadFET) diagnostics? Beam current for Rahima's QDC tests in A1? Possible to find back the dose accumulated during the beamtime in June 2023? (-> Rahima, Jurgen)
 - 
MESA beam tube and flange dimensions? (-> Kurt, ...?)
 - 
picture of shielding rails in scattering chamber (-> Boris)
 - 
beam polarity pattern and signals?
 - 
Availability of clean GND (EARTH) in the P2 experimental hall
 
Mainz questions to IRFU
- 
How expell the Isobutane? exhaust setup : ~20m high, 40 or 80 mm diameter. IRFU : Clarify ATLAS, Clas12 setups; transmit to P2
 - 
short-term storage (~100 Tb) : decide within 6 months. Long-term : decide by 2026. Clarify commissioning strategy in this respect.
 